Lake Kariba dam wall structural rehabilitation to commence in February 2017

Work on the long-awaited rehabilitation of the Kariba Dam wall, which hosts the giant Kariba Hydro-Electric Station that generates electricity for Zimbabwe and Zambia is set to commence in February 2017, the Zambezi River Authority (ZRA) has announced.

Addressing journalists in the southern Zambian town of Livingstone this week, ZRA chief executive officer, Munyaradzi Munodwafa, said work on the main component, which would be focused on a re-modelling of the plunge-pool to minimise a scouring of its foundations, would commence in February 2017 and continue up to early 2020.

Advanced repair works on all six spill-way gates around the dam wall are set to commence in July 2017 and continue up to July 2024. As of April 2015, the total project cost was estimated at US$ 294 million, which would be released in batches spread over the duration of the works.

“Tenders for the contractors to carry out works on the plunge pool will close on October 23, 2016, and for the sluice gates tenders will be opened in November while the bidder is expected to be appointed by June next year. Without functional sluices, the reservoir level cannot effectively be maintained to take into account the flood regime of the Zambezi River,” he said.

The project was funded by partners who include the European Union, the World Bank, the African Development Bank and the government of Sweden to help the governments of Zimbabwe and Zambia avert a possible collapse of the dam wall.

Apart from economic losses arising from the destruction of the hydro-power investments, a collapse of the Kariba Dam wall would generate a regional humanitarian crisis arising from flooding.